Norway halts new data center grid reservations.
Reservation pause extends until at least August 2027.
Norway's transmission system operator Statnett paused new grid reservations for data centers on 9 November, coinciding with a government licensing scheme restricting new crypto mining. The halt under Regulation on System Responsibility (fos) § 14 covers functional requirements for data centers, including connection stability during disturbances. Projects with reserved capacity retain their position but require approval before actual connection, while existing links remain unaffected.
Data centers have requested about 34 gigawatts of capacity, exceeding Norway's national peak demand of approximately 25 gigawatts. Only 0.8 gigawatt is currently connected, with 4.2 gigawatts in reserved status, 10.8 gigawatts in the queue, and 18 gigawatts still at the inquiry stage. The new system slated for implementation by August 2027 will manage grid fluctuations and set operational thresholds, delaying further capacity additions.