S&P 5007,182.78▼0.2% Nasdaq23,585.80▼0.6% Dow50,182.95▲0.3% Russell 2K2,704.06▲0.7% 10-Yr4.85%−6bp VIX28.29+1.93 WTI$84.31▲2.8% Gold$3,604.30▲1.2% EUR/USD1.097▲0.0% BTC$60,426▲0.1% Nikkei57,887▲1.5%
At close · Wed, Nov 25, 2026
Daily Market Updates.

Commodities

Home›Commodities›Energy›Norway halts new data center grid reservations.

Norway halts new data center grid reservations.

Reservation pause extends until at least August 2027.

Norway's transmission system operator Statnett paused new grid reservations for data centers on 9 November, coinciding with a government licensing scheme restricting new crypto mining. The halt under Regulation on System Responsibility (fos) § 14 covers functional requirements for data centers, including connection stability during disturbances. Projects with reserved capacity retain their position but require approval before actual connection, while existing links remain unaffected.

Data centers have requested about 34 gigawatts of capacity, exceeding Norway's national peak demand of approximately 25 gigawatts. Only 0.8 gigawatt is currently connected, with 4.2 gigawatts in reserved status, 10.8 gigawatts in the queue, and 18 gigawatts still at the inquiry stage. The new system slated for implementation by August 2027 will manage grid fluctuations and set operational thresholds, delaying further capacity additions.

More like this

Sources

Get the close, explained.

One email every trading day: what moved, why it moved, and what's on deck tomorrow. Read in 3 minutes.

Free. Unsubscribe anytime.